IAN KREMMER

MANAGING DIRECTOR

KREMMER MANAGEMENT GROUP

Ian Kremmer Photo.png

QUALIFICATIONS

  • Bachelor of Engineering BE (Hons) - University of Tasmania

  • Master of Business Administration (MBA) - Deakin University

  • PRINCE2 Practitioner

  • CP3O Portfolio Management Foundation

  • Academy of Experts (UK) Introduction & Advanced Courses

 

MEMBERSHIPS

  • Member of Institution of Engineers Australia (MIE Aust)

  • Member of Academy of Experts UK (MAE)

  • Member of Society of Construction Law Australia (SOCLA)

PROFILE

  • Ian Kremmer is a qualified civil / structural engineer with over 40 years of extensive project, engineering, construction and management consulting experience gained across a very wide range of civil engineering, building, infrastructure, transport, mining and IT projects working for Tier 1 Contractors, design and management consultants, government organisations and private owners within Australia and overseas.

 

  • Ian provides Expert Witness Delay and Disruption analysis services together with Lead Planner and Project Advisory  roles on current major infrastructure projects.

 

  • Ian has specialist knowledge and experience in project and construction planning, detailed scheduling and analysis, construction planning, staging and methodology, constructability advice, design and project control and procurement systems, schedule performance and risk analysis, tendering, Building Information Modelling (BIM) Systems, temporary works design, structural engineering, last planner (Lean Construction) and developing and implementing program and portfolio management systems.

 

  • Ian has a high level of technical and analytical capability and has practical knowledge of industry standard software products such as Primavera P6, Microsoft Project, Asta Powerproject, Navisworks BIM, @Risk for Microsoft Project, Acumen Fuse and Risk, Microsoft Access, Microsoft SQL Server and Microsoft Reporting Services.

PROJECT EXPERIENCE

 

EXPERT WITNESS & CONTRACT CLAIMS

Expert Witness Delay & Disruption Report - Port Pirie Transformation Project (KMG, 2019/20)

  • Preparation of Delay & Disruption Expert Witness Reports for Contractor Supplier for the purpose of Arbitration in relation to a major delay & disruption claim at the Nyrstar Port Pirie project in South Australia. Preparation for Supreme Court Arbitration Hearing.

Expert Witness Delay & Disruption Report - Port Pirie Transformation Project (KMG, 2019/20)

  • Preparation of Delay & Disruption Expert Witness Reports for Contractor Supplier for the purpose of Arbitration in relation to a major delay & disruption claim at the Nyrstar Port Pirie project in South Australia. Preparation for Supreme Court Arbitration Hearing.

Expert Witness Delay Report - EOT Delay Claim - Vancouver G3 Grain Terminal - Structural Steel Fabrication (KMG, 2019)

  • Preparation of Delay Expert Witness Report for the purpose of Arbitration for the Australian Supplier in relation to an extension of time claim for the Grain Terminal Project in Vancouver, Canada for delays incurred to China structural steel fabrication and delivery.

Expert Delay Analysis Report - EOT Delay Claim - Houston, Texas, USA - Structural Steel Fabrication (KMG, 2019)

  • Preparation of Delay Analysis Report for the purpose of Mediation for the Australian Supplier in relation to an extension of time claim for a major Terminal Project in Houston, Texas USA for delays incurred to China structural steel and piping fabrication and delivery.

Delay Claim Analysis - Blackrock Water Treatment Plant (KMG, 2019)

  • Preparation of Delay Claim Analysis report for the purpose of mediation on behalf of Contractor in relation to delays incurred at the Black Rock Water Treatment Plant in Geelong Victoria (2019).

Expert Witness Delay Report - Station Street Retail Development, Subiaco Western Australia (KMG, 2018)

  • Preparation of Delay Expert Witness Report for the purpose of Adjudication and Arbitration on behalf of Head Contractor in relation to delays incurred during construction of the Station Street Retail Development in Perth.

Expert Witness Delay Report - BHP Ore Car Workshop, Port Hedland, Western Australia (HKA, 2018)

  • Preparation of Expert Witness Report on behalf of the Main Contractor for the purpose of Arbitration in relation to delays incurred during construction of the BHP Ore Car Workshop at Port Hedland, Western Australia.

Expert Witness Delay Report & Arbitration Hearing - Richmond Quarter Multi-storey Apartment Complex, Fremantle (HKA, 2017)

  • Preparation of Delay Expert Witness Report on behalf of Owner / Developer. preparation of Joint Expert Report and attendance at Arbitration hearing hot-tubbing session over two full days.

Expert Witness Delay Report & Arbitration Hearing - Karratha Cultural Centre, Western Australia (HKA, 2017)

  • Preparation of Expert Witness Delay Report on behalf of Contractor. Cross examination in Arbitration hearing.

Expert Delay Claim Report - Cape Lambert Power Station (Rio Tinto Project): (HKA, 2017)

  • Preparation of Expert Delay Claim Report in relation to delays that occurrent on behalf of the Main Contractor during procurement.

Expert Delay Claim Report - Midland Hospital, Perth, Western Australia (HKA, 2017)

  • Preparation of Expert Witness Delay Claims Analysis Report for the purpose of Mediation on behalf of the Main Contractor in relation to delays incurred and the Midland Hospital Project in Perth.

Expert Witness Delay Report - Kingsford Smith Drive Extension, Brisbane (HKA, 2017)

  • Preparation of an Expert Witness Adjudication Delay Report on behalf of the Main Contractor in relation to delays incurred during construction of the Kingsford Smith Drive Extension Project in Brisbane.

Expert Delay Claim Report - Shell House Fitout, Perth, Western Australia (KHA, 2017)

  • Preparation of an Expert Delay Claim Report on behalf of Owner for the purpose of Mediation in relation to delays incurred during construction of the Shell House Fitout in Perth.

Expert Witness Quantum Report - Port Hedland Accommodation Facility - (Hill International, 2016)

  • Preparation of Expert Witness Quantum Report in relation to defects for 1,000 accommodation unit permanent accommodation camp at Port Hedland, including site condition survey and liaison with Technical Experts to assess liability and hold Joint Expert Conferral Meeting.

Expert Witness Delay Report - Gorgon Construction Village Buildings, Western Australia - (Hill International, 2016)

  • Preparation of Expert Witness Report - Delay & Disruption analysis on behalf of EPC Contractor. (Hill International, 2014 and 2015)

Expert Witness Delay Report - Gorgon Project Storage Tanks, Barrow Island, Western Australia (Hill International 2016)

  • Assistance with preparation of Expert Witness Delay Report on behalf of EPC Contractor (Hill International, 2015 to 2016) in relation to delays incurred during construction of the Gorgon Project Storage Tanks at Barrow Island., Western Australia

Delay Claim Review - Inpex / Ichthys Permanent Buildings (Hill International, 2016)

  • Assistance with preliminary review of delays and actual progress for EPC Subcontractor.

Expert Delay Claim - Report - Wheatstone Permanent Buildings (Hill International, 2015 and 2016)

  • Preparation of Expert Delay Claim Report in relation to the delays that occurrent to twelve major buildings on behalf of the EPC Subcontractor for design, procurement and construction.

Delay Claim Report - New Perth Library, Perth - (Hill International, 2015)

  • Undertook independent review of EOT claims and actual progress and critical delays on behalf of the Superintendent for the New Perth Library.

Delay & Disruption Claim Report - Gas Pipeline Project, Queensland - (Hill International, 2015)

  • Assistance with preparation of a detailed measured mile disruption analysis on behalf of the EPC Contractor in relation to labour productivity and disruption that occurred on a major gas pipeline infrastructure project.

Expert Delay Claim Report - Wheatstone Permanent Buildings - Disruption Claim (Hill International, 2015)

  • Preparation of Expert Disruption Claim  on behalf of the EPC Subcontractor, including review of labour records and undertaking a detailed measured mile disruption analysis.

Delay Claim Review - Osborne Park Office Building - (Hill International - 2015)

  • Undertook review of EOT claim and assessment of delays and concurrency for building owner.

Expert Witness Delay Report - Gorgon Permanent Buildings and Facilities, Barrow Island, Western Australia (Hill International, 2014 to 2015)

  • Preparation of Expert Witness Delay Report in relation to delays that occurred in relation to construction of the project on behalf of the EPC Contractor.

Expert Witness Delay Report - Wiggins Island Coal Export Terminal Bridge Fabrication, Queensland (Hill International, 2014)

  • Preparation of an Expert Witness Delay Report in relation to delays that occurred on the project on behalf of the Construction Contractor, including assessment of bridge fabrication in China and related shipping delays.

 

PROCESS PROJECTS

 

Rockingham Waste to Energy Project for Acciano - Lead Planner ($550m EPC) (Acciano, 2019 to 2020)

  • Planning Consultant engaged by Acciona on $550m EPC process plant. Responsible for preparation of tender programme, contract programme Master Schedule and preparation of monthly updates for design, procurement and construction on a complex process plant.

Kwinana Waste to Energy Project for Acciano - Lead Planner ($720m EPC) (Acciano, 2018 to 2020)

  • Lead Planner engaged by Acciona on $720m EPC process plant. Responsible for preparation of Master Schedule and preparation of monthly status reports for design, procurement and construction. on a complex process plant.

Nyrstar Smelter Shutdowns: Schedule Risk Analysis (Beca, 2002 to 2004)

  • Developed detailed Monte Carlo risk analysis schedules using @Risk Project software for smelter operational shut-downs for Nyrstar at the Port Pirie and Hobart process plants.

 

TRANSPORT PROJECTS

Construction Advisor - Project Review - Major NSW Department of Transport Road & Tunnel Project (KMG 2020)

  • Construction Advisor undertaking project review on major NSW Department of Transport Road & Tunnel Project.

Sydney Metro West Project - Lead Planned & Schedule Risk Analysis (HKA/KMG 2018)

  • Lead Planner Role: Master Schedule for NSW Government Transport Business Case (HKA – Mar 2018 to August 2018 / KMG September 2018 to April 2019) - Australia’s largest single infrastructure project valued at $20 billion. Responsible for preparation of the Master Schedule to support the NSW Government Business Case.

Westconnex M4 & M5 Road Tunnels: NSW Asset Sale - Schedule Risk (HKA - 2018)

  • Schedule Risk Advisor to Purchaser: Provided Schedule Risk advice to IFM Investors Pty Ltd - (HKA – March 2018 to July 2018) Provision of Schedule Risk advice to Purchaser during the sale process for Westconnex.

Great Northern Highway Realignment Project at Port Hedland: Project Planning & Controls Manager (Macmahon / John Holland, 2012 to 2013)

  • Responsible for developing and implementing the fully resourced Project Master Schedule, preparation of detailed procurement and resource plans, developing and implementing project controls for the GNH $280 million design & construct project. ​

  • Responsible for preparation of monthly status reports, updating site construction programmes, establishing design and procurement monitoring systems, preparation of EOT claims and providing on-going project and strategic advice.

  • This project includes in excess of 2.5 million cubic metres of earthworks, three major overpass bridges (including two over the BHP Rail line) and two major drainage culvert structures.

Lloyd Street Underpass (Perth) - Tender Programme (John Holland, 2013)

  • Responsible for preparation of a detailed tender programme for the design and construction of a complex underpass in Perth, including staging, bridge construction and rail shut down and relocation.

Seaford Rail Extension: Tender Programmes (Baulderstone/York Civil Joint Venture - 2007)

  • Preparation of Tender Programmes for Seaford Extension Rail Link in Adelaide, including provision of strategic advice and programme development and 4D virtual construction modelling.

South Road Project, Adelaide: Tender Program (Baulderstone / York CIvil Joint Venture, 2006)

  • Preparation of Tender Programmes for South Road Project in Adelaide, including provision of strategic advice and programme development.

Jolimont Rail Redevelopment, Melbourne: Master Program (Major Projects Vic, 1996)

  • Preparation and on-going development of Master Programme for relocation of 54 rail lines to 12 rail lines, construction of new walls to support the Federation Square platform and relocation of CBD maintenance facilities to outer Melbourne locations.

MCG Southern Stand, Melbourne - Project Planning (John Holland, 1990)

  • Detailed programme and staging for MCG Southern Stand precast ramps and walkways.

James Harrison Balanced Cantilever Bridge, Geelong: Site Project Engineer (Lewis Constructions, 1988)

  • Site Engineer responsible for erection and operation of balanced cantilever traveller for construction of 80m span bridge of the James Harrison Bridge over the Barwon River, Geelong.

PORT PROJECTS

Fremantle Port and BHP Rail Projects: Tender Programme (Abigroup, 2013)

  • Prepared tender programmes for Abigroup (now Lend Lease) for the Fremantle Port North Quay Rail Terminal Expansion Project and the BHP Ore Car Rail Project.

Port of Melbourne Expansion Project: Construction Planning & Schedule Risk Analysis (Port of Melbourne Corporation, 2013)

  • Responsible for management and review of detailed Construction Schedule for this project. The Construction Schedule was fully resourced and a Basis of Schedule was prepared for the schedule.

  • Undertook detailed Monte Carlo Risk Schedule Analysis for the Construction Schedule and a high level Risk Analysis for the Project Master Schedule.

 

BUILDING PROJECTS

Nakheel Tall Tower - World’s Tallest Building High Rise Project, Dubai (1.2 km high /250 storeys) - Master Programme and Schedule Risk Analysis (Nakheel,2007)

  • Development of a Master Construction Programme and Monte Carlo risk analysis for the Nakheel NTT (world’s tallest tower project in Dubai). Review of constructability with Building Contractor in Tokyo.​

  • Development of a Master Schedule and Monte Carlo risk analysis for the Nakheel NTT (world’s tallest tower) project in Dubai.

Vision 80 Storey High Rise Complex, Brisbane:Construction Planner (Grocon, 2009 to 2010)

  • Detailed construction planning and programming for the $500 million 80 storey high- rise building Vision Tower retail, commercial and residential project in Brisbane.

Australand Apartments - North Edge Project (Australand, 2002)

  • Provision of project planning, controls, monitoring and engineering services.

National Gallery of Victoria, Melbourne Master Programme (Major Projects Victoria, 1997)

  • Preparation of Master Programme at inception of project and on-going development and monitoring during the design phase for Major Projects of Victoria.

Docklands (ETIHAD) Stadium, Melbourne: Master Program (Major Projects Victoria, 1997)

  • Preparation of Master Programme at inception of project.

Federation Square, Melbourne: Master Program (Major Projects Victoria, 1997)

  • Preparation of Master Programme at inception of project.

Melbourne Central Tower & Retail Development - Construction Engineering and Planning (Lewis Constructions Victoria, 1989 to 1990)

  • Preparation and monitoring of site construction programmes and construction engineer responsible for Melbourne Central Cone temporary works, Melbourne Central Tower (55 storeys) temporary works and planning and erection of Melbourne Central Antenna Masts.

530 Collins Street - Construction Engineering (Lewis Constructions Victoria, 1990)

  • Construction engineer responsible for temporary works design for tower crane tie design and screens.

 

OIL & GAS PROJETCS

Icthys/Inpex CVL-3 Civil and Underground Works Project, Last Planner Systems Development & Implementation (Leighton Contractors, 2013)

  • Responsible for designing, developing and implementing a Last Planner Database System for this project. The purpose of this comprehensive database system has been to provide accurate and reliable daily reporting to the client and internally including labour, plant, progress and production issues, weather, industrial, safety and other information.

  • The system also captures weekly planning and daily monitoring of production and productivity based upon bill items and provides comparisons between earned and actual plant and labour hours and planned versus actual production. Responsible for implementing Navisworks BIM development and data extraction to facilitate procurement tracking.

Gorgon Civil and Underground Services: Project Planning & Controls Manager and Precast Procurement Database Development (Leighton Contractors, 2011 to 2012)

  • Engaged as consultant Project Controls Manager, provided expert planning and scheduling advice and responsible for development and submission of the Master Construction Schedule.

  • Responsible for development of a database control systems to track quantities of materials, resources and productivity changes and labour estimates.

  • Established comprehensive procurement tracking system to manage precast fabrication (65,000 components) including development of reports and daily monitoring of design variations, procurement, shipping, logistics and site installation.

  • Developed multi-user database to manage scope changes.

Resak Onshore Oil Refinery, Kijal, Malaysia: Project Planning & Controls (Contractor, 1997)

  • Prepared site project programmes to support the construction project in Malaysia.

 

MINING PROJECTS

 

Copper Mine Tailings Projects: Project Planning & Controls Manager and Assistant Project Manager - Iran (Australian Tailings Consultants, 2004 to 2008)

  • Project Planning and Controls Manager and Assistant Project Manager for Tailings Disposal System for the Sungun, Sar Cheshmeh and Miduk Copper Mines in Iran.

  • Development of cost plans, programs, studies, design and engineering, including detailed analysis for Pre-Feasibility and Feasibiity Reports for the Sungun and Sar Cheshmeh projects. From 2004 to 2008, Ian had 18 site visits to the support the Iran tailings projects.

Batu Hijau Copper Mine: Site Project Planner, Construction Engineer and Project Controls for Earthworks, Sumbawa, Indonesia (John Holland, 1998)

  • Development of detailed earthworks construction programme with plant and equipment resourcing.

  • On-site project planning and project engineering support. Extensive earthworks project with monthly production exceeding 1 million cubic metres per month.

Oakajee Port & Rail Project: Master Programme & Project Planning Consultant (Oakajee Port & Rail, 2008)

  • The Oakajee Port and Rail Project was valued at $5 billion and involved a major port development and 500km of rail infrastructure. Services included preparation and development of the project Master Program in Primavera P6 including detailed scheduling of design and construction tasks, environment planning, indigenous and land approvals and legal and financial closure requirements and evaluation of program scenarios and risk scenarios.

  • Development of Master Schedule, including legal and approval processes, for the Oakajee Port and Rail Project which was valued at $5 billion and involved a major port development and 500km of rail infrastructure.

Port Headland Outer Harbour Quantum Project: Master Programme & Procurement Strategy Programme (BHP / AECOM, 2010)

  • Provision of specialist planning and scheduling advice and preparation of numerous high level strategic Master Programmes for the Port Headland Outer Harbour Development. Review of contract and construction programs, project scenarios and risks.

Olympic Dam: Master Programme for Pre-Feasibility Study (BHP / AECOM, 2009)

  • Preparation of the Master Program in Primavera P6 for the Pre-Feasibility Stage, including review and consideration of numerous options for the project, including resource loading.

Goro Nickel Mine, New Caledonia: Cost & Productivity Systems (Goro Nickel, 2006)

  • Development of database system to plan and monitor earthworks progress and productivity for major dam construction at Goro Nickel Mine.

Madagascar QMM Port Development (Rio Tinto): Project Planning and Construction Progress & Productivity Control System (Rio Tinto, 2006 and 2007)

  • Preparation of the Master Program for the project from design through to construction and handover. Development of a comprehensive database to monitor site progress in detail, including daily production and diary records for quarry and breakwater construction. The system allowed Rio Tinto to accurately assess contractor performance and contractual claims.

AIRPORT PROJECTS

Melbourne Airport A380 Runway Widening: Project Planning & Controls Systems and Constructability Advice (Melbourne Airport, 2003 to 2004)

  • This was identified as a very a high-risk project which involved the complete shutdown of the main runway at Melbourne Airport for a period of one month to widen the runway to accommodate A380 aircraft and to install a CAT II lighting system. The project was successfully completed without one day loss against the original schedule and won the coveted industry Construction Achievement Award which is awarded annually for the most successful Australian construction project.

  • Planning advisor reporting directly to Melbourne Airport, from inception to completion, for all aspects of this project, which was logistically complex due to large quantities and risks associated with the shut-down. Ian provided detailed planning of the early works, including intersection upgrades and developed a daily progress monitoring system for reporting directly to senior airport staff.

Melbourne Airport T2 International Terminal Expansion: Master Programme & Constructability Advice (Melbourne Airport - 2006 to 2009)

  • $330 million expansion of the international terminal and associated airfield and building projects for Melbourne Airport. This project involved redevelopment of the International Terminal, including additional Gates, Lounges, Retail Facilities and Baggage Systems. The project was successfully completed on-time and on-budget.

  • Provision of strategic planning, construction staging and project monitoring advice directly to Melbourne Airport, from inception through to completion, including attendance at Project Control Group Meetings.

Melbourne Airport T3 Domestic Terminal Expansion: Master Programme and Constructability Advice (Melbourne Airport – 2008)

  • Provision of strategic planning, construction staging and project monitoring advice directly to Melbourne Airport during the planning phase of this project, including attendance at Project Control Group Meetings.

Melbourne Airport Master Schedule Development: Planning Consultant (Melbourne Airport, 2006 to 2010)

  • Development of numerous Master Schedules for individual projects and programs and to provide advice regarding interface management and procurement and contracting strategy to enable coordination of projects within Melbourne Airport.

Melbourne Airport Taxiway & Western Apron: Master Programme & Constructability Advice (Melbourne Airport, 2007 to 2008)

  • Provision of Master Programme, planning, programming and constructability advice and detailed development and construction programme.

  • Detailed scheduling, 4D construction planning, interface planning and progress monitoring of aprons and taxiways adjacent to the new International Terminal Expansion.

Melbourne Airport  A380 ART Buildings: Master Programme & Constructability Advice (Melbourne Airport, 2003 to 2004)

  • Master programming, staging ad-vice, evaluation of construction options, general risk management advice in relation to runway widening, aircraft parking apron extension, terminal and aerobridge works for new Airbus A380 aircraft.

  • Detailed planning and progress monitoring of A380 runway widening.

Australian Advanced Airport Traffic System (TAAATS) Project, Project Manager / Design Manager (John Holland, 1994 to 1996)

  • National Project Manager and Design Manager for $40 million project involved the design and construction of building works and base infrastructure services requiring a high degree of technical complexity and reliability.

Ansett Passenger Terminal Development Project: Master Programme and Constructability Advice (Ansett, 1998 to 2000)

  • Provision of Master Programme, planning, programming and constructability advice during design and construction.

Ansett Olympic Expansion: Project Planning & Contract Administration Control Systems (Ansett, 1999)

  • Development and implementation of project control systems during construction. Monitoring of construction progress and site coordination.

Sydney International Airport Terminal Expansion Airport 2000 Infrastructure Master Planning for Federal Airports Corp (1997)

  • Detailed review of constructability, programme, procurement, design and construction methods; assessment of resources, project risks and review of staging options.

Brisbane Domestic Airport Expansion: Tender Programme (Grocon, 2009)

  • Preparation of detailed tender programme and staging analysis for the Brisbane Domestic Airport Expansion project).

PORTFOLIO & PROGRAM MANAGEMENT

Melbourne Airport Capital Planning System: Portfolio and Program Management System Design, Development, Implementation and Support (Melbourne Airport, 2006 to 2010)

  • Development and implementation of capital works planning and monitoring systems for Melbourne Airport Corporation of the capital project portfolio over a 20year planning horizon, including development and documentation of business processes, systems design and database development, development of 10 Year Plans and Annual budget planning.

  • Provided advice and developed Capital Planning systems, including development and documentation of business processes, systems design and database development, development of 10 Year Plans and Annual budget planning.

  • Provided strategic project advice regarding procurement methodologies, construction methods, planning, programming and monitoring of numerous other projects to support Melbourne Airport.

 Port of Melbourne Capital Planning & Management: Portfolio & Program Management System Design, Implementation and Support (Port of Melbourne, 2010 to 2013)

  • Responsible for the development and implementation for a comprehensive web-based capital works monitoring system to track all projects and programs over the project life cycle from inception through to final handover, including tracking of project gates, schedule milestones, project costs, cash flows, forecast costs and variations and the ability to undertake detailed reporting of costs and schedule at the work package level.

Monash University, Victoria: Program Management System Design, Development, Implementation and Support (Monash University, 2009 to 2010)

  • Development of capital planning systems to plan, manage and monitor all capital works projects from inception through to completion, including monitoring of cash flows, changes, risks, contract work packages and costs.

Melbourne Metro Rail Projects, Melbourne: Program Management System Design, Development and Implementation (Connex/Metro Joint Venture)

  • Development of project monitoring systems to manage the program of all rail works.

Coles Supermarkets National Division: Capital Planning System Design, Development & Implementation for Program Management (Coles Myer) 2007

  • Development of program management and control system for national supermarket development – estimated capital cost per annum $400 million for approximately 400 projects. This work involved review, development and documentation of business processes for project delivery and establishment of effective corporate and project level reporting and monitoring systems for KPI performance, financial and business reports.

INFORMATION TECHNOLOGY PROJECTS

Skilled Business System: IT Project Manager (Skilled Group, 1997 to 2000)

  • Project Manager responsible for the specification, design, development, installation, training, change management, data migration and rollout of a new national business system for Skilled Engineering Ltd with an annual turnover exceeding $600 million.

CORPORATE PLANNING ROLE

State Planning Manager:  Victoria, South Australia & Tasmania Planning Manager (John Holland, 1991 to 1994)

  • Planning Manager for John Holland’s Southern Region: Responsible for tender and construction planning, engineering, value analysis and provision of planning support systems within the Victoria, SA and Tasmania region. During this time, the company undertook such projects as the Toyota Factory, MCG Great Southern Grandstand, ABC Studios in Melbourne.